Test4Sure 070-178 questions and answers provide you test preparation information with everything you need. Study with our 070-178 test practice materials, your professional skills will be enhanced and your knowledge will be expanded. What's more, 070-178 practice pdf will ensure you a define success in our 070-178 actual test.
Test4Sure has an unprecedented 99.6% first time pass rate among our customers.
We're so confident of our products that we provide no hassle product exchange.
| Certification Vendor: | Microsoft |
| Exam Name: | Microsoft Project 2010, Managing Projects |
| Exam Number: | 70-178 |
| Certificate Validity Period: | Retired (no active validity; exam retired July 31, 2015) |
| Exam Price: | US$125 (varies by region) |
| Related Certifications: | Microsoft Certified Technology Specialist (MCTS) 70-177: Microsoft Project Server 2010, Configuring |
| Exam Duration: | 150 minutes |
| Exam Format: | Multiple choice, Case study, Performance-based items |
| Real Exam Qty: | 50-55 |
| Passing Score: | 700 (scaled from 1000) |
| Available Languages: | English, French, German, Italian, Japanese, Spanish |
| Recommended Training: | MPUG Project 2010 Training Resources Microsoft Official Course 50589: Managing Projects with Microsoft Project 2010 |
| Exam Registration: | Microsoft Learning (Retired Exam) |
| Sample Questions: | Microsoft 070-178 Sample Questions |
| Exam Way: | Proctored computer-based exam (originally delivered via Prometric/Certiport centers) |
| Pre Condition: | Recommended: 6+ months practical experience using Microsoft Project Standard 2010 or Professional 2010; understanding of basic project management concepts |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/certifications/retired-certification-exams |
| Section | Weight | Objectives |
|---|---|---|
| Viewing and Reporting Project Data | 20% | - Customize views and tables
|
| Creating a Project Plan | 20% | - Create task relationships
|
| Managing Resources and Assignments | 25% | - Assign resources to tasks
|
| Configuring and Automating Projects | 10% | - Customize Project 2010 environment
|
| Tracking and Controlling Projects | 25% | - Monitor schedule and costs
|
1. You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
A) Fill Down
B) Insert Summary
C) Outdent
D) Move Task
2. You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?
A) In the Start Date field, type 9/13/2010.
B) Change the Status Date field to 9/13/2010.
C) In the Current Date field, type 9/13/2010.
D) Change the calendar type in the Project Options dialog box.
3. You use Project Professional 2010 to manage a project. John, a team member, is over-allocated. You need to identify the dates on which the over-allocation occurs. What should you do?
A) Use the Team Planner view.
B) Use the Timeline view.
C) Use the Task Details Form.
D) Use the Task Information dialog box.
E) Use the default Leveling Gantt view.
4. You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
A) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Entire Project radio button, and then click OK.
B) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
C) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
D) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.
5. You create several new tasks by using the Manually Scheduled Task option. You need to automatically calculate the start and finish dates for linked manually scheduled tasks. You need to achieve this goal while retaining manually scheduled tasks within the project. What should you do?
A) Highlight the Project Summary task and use the Calculate Project feature.
B) Insert the task Constraint Type column and change the values for each task to the appropriate values. Then, recalculate the project.
C) Modify the values of Scheduled Start and Scheduled Finish.
D) Use the Respect Links feature.
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: A | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: D |
When you learn from best, you can surly pass 070-178 your test easily.
Passd 070-178
What about 74-679 exam? It is my next one.
We really appreciate it for the dump 070-178
To my surprise, I passed the 070-178 test easily.
Valid 070-178 dumps, I passed the test.
Today was my 070-178 exam day and I made a great hit in it.
Disclaimer Policy: The site does not guarantee the content of the comments. Because of the different time and the changes in the scope of the exam, it can produce different effect. Before you purchase the dump, please carefully read the product introduction from the page. In addition, please be advised the site will not be responsible for the content of the comments and contradictions between users.
Test4Sure focus on the study of 070-178 practice questions for many years and enjoy a high reputation in this field by its high-quality study materials, updated information. From the 070-178 free demo, you will have an overview about the complete exam materials. The comprehensive questions together with correct answers are the guarantee for 100% pass.
Besides, we have money back guarantee to ensure customers' benefit in case of failure. You just need to show us your failure certification,then we will give you refund after confirming.
Firstly,the contents of the three versions are the same. Besides, the PC test engine is only suitable for windows system wiht Java script,the Online test engine is for any electronic device. While, the pdf is pdf files which can be printed into papers.
Yes, 070-178 exam questions are valid and verified by our professional experts with high pass rate. The contents of 070-178 study materials are most revelant to the actual test, which can ensure you sure pass.
All our products are the latest version. If you want to know details about each exam materials, our service will be waiting for you 7*24 online. Our exam products will updates with the change of the real 070-178 test.
You will get an email attached with the 070-178 study materials within 5-10 minutes after purchase. Then you can download it for study soon. If you do not receieve anything, kindly please contact our customer service.
All our products can share 365 days free download for updating version from the date of purchase. So don't worry. The exam materials will be valid for 365 days on our site.
Sure, we offer the 070-178 free demo questions, you can download and have a try. Besides, about the test engine, you can have look at the screenshot of the format.
We have professional system designed by our strict IT staff. Once the 070-178 exam materials you purchased have new updates, our system will send you a mail to notify you including the downloading link automatically, or you can log in our site via account and password, and then download any time. As we all know, procedure may be more accurate than manpower.
Yes, we have money back guarantee if you fail exam with our products. Applying for refund is simple that you send email to us for applying refund attached your failure score scanned. Money will be back to what you pay. Normally we support Credit Card for most countries. Our refund validity is 60 days from the date of your purchase. Our customer service is 365 days warranty. Users can receive our latest materials within one year.
Self Test Software can be downloaded in more than two hundreds computers. It is no limitation for the quantity of computers. So does Online Test Engine. You can use Online Test Engine in any device.
Sure, we have discounts for promotion in some specail festival.
Over 59464+ Satisfied Customers