2024 Valid AACE-PSP Real Exam Questions (Updated) 100% Dumps & Practice Exam
[UPDATED 2024] AACE International AACE-PSP Questions Prepare with Free Demo of PDF
The AACE-PSP Certification Exam is recognized worldwide and is highly valued by employers in the industry. It is a rigorous exam that tests the candidate's knowledge in various areas related to project planning and scheduling. AACE-PSP exam covers topics such as project planning, scheduling techniques, resource management, risk management, and communication management.
NEW QUESTION # 25
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
- A. Predecessor is activity 9001, successor is activity 9002
- B. Predecessor is activity 5001, successor is activity 8002
- C. Predecessor is activity 4001, successor is activity 8001
- D. Predecessor is activity 5001, successor is activity 8001
Answer: D
NEW QUESTION # 26
What is the relationship depicted between Activity G and Activity H?
- A. Finish-to-start.
- B. Start-to-start.
- C. You cannot tell with the supplied information.
- D. Finish-to-finish.
Answer: B
NEW QUESTION # 27
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 7 work days
- B. 8 work days
- C. 15 workdays
- D. 18 work days
Answer: B
NEW QUESTION # 28
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- B. It assumes that resources are unlimited.
- C. It doesn't account for interdependent between activities.
- D. It requires a backward pass to calculate late dates.
Answer: B
NEW QUESTION # 29
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-18-02.
- B. 06-05-02.
- C. 06-04-02.
- D. 06-11-02.
Answer: B
NEW QUESTION # 30
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A. Use the progressed portion of the critical path of all the updates previous to the current update.
- B. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- C. Use the progressed portion of the critical path of the baseline schedule.
- D. Use the forward-looking critical path of the most current updates.
Answer: D
NEW QUESTION # 31
Identify the minimum project duration.
- A. 19 months.
- B. 16 months.
- C. 21 months.
- D. 20 months.
Answer: D
NEW QUESTION # 32
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
- A. 2.
- B. 1.
- C. Does not change.
- D. 3.
Answer: C
NEW QUESTION # 33
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 15 days.
- B. 5 days.
- C. 0 days.
- D. 10 days.
Answer: C
NEW QUESTION # 34
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must affect the critical path.
- B. The delay must affect the contractor's planned construction schedule.
- C. The delay must be concurrent with the delay attributable to both parties.
- D. The delay must not cause monetary harm to the defendant.
Answer: A
NEW QUESTION # 35
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS.10002 - Lag.7 - l day -> 11-20-03.
- B. LS.10002 + 1 day -> 11-29-03.
- C. LS.10002^ Lag.7 + i day -> 11-20-03.
- D. LS.10002 - 1 day -> 11-27-03.
Answer: C
NEW QUESTION # 36
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-17-03 and 4 days of float
- B. 12-27-03 and 24 days of float
- C. 12-18-03 and 4 days of float
- D. 12-18-03 and 25 days of float
Answer: A
NEW QUESTION # 37
Estimate to complete (ETC) is __________________.
- A. The expected total cost of an activity, group of activities or the project
- B. The costs actually incurred in accomplishing the work performed
- C. The value of the completed work expressed in terms of the budget assigned to that work
- D. The expected remaining cost needed to complete an activity, group of activities or the project
Answer: D
NEW QUESTION # 38
The work breakdown structure is used to organize
- A. The smallest defined work packet
- B. The chart of accounts
- C. Similar activity coding of schedule activities
- D. "Smart activity ID codes" representing similar items of scheduled work
Answer: A
NEW QUESTION # 39
Which of the following will always describe the critical path? The path with
- A. The shortest duration and negative float.
- B. The longest duration through the network.
- C. Zero float.
- D. Negative float.
Answer: C
NEW QUESTION # 40
What problems can a soils engineer deal with on a project?
- A. Survey error.
- B. Hidden subsurface conditions.
- C. Toxic soils.
- D. Archeological findings.
Answer: B
NEW QUESTION # 41
An early start constraint dictates
- A. An activity's remaining duration.
- B. The planned start of an activity.
- C. The planned start of a successor activity
- D. The actual start of an activity.
Answer: C
NEW QUESTION # 42
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
- A. 20 lifts
- B. 80 lifts
- C. 5 lifts
- D. 50 lifts
Answer: D
NEW QUESTION # 43
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
- A. Delay manufacturing by 5 days.
- B. Expedite printing by 5 days.
- C. Delay product release by 5 days.
- D. Expedite packaging by 5 days.
Answer: C
NEW QUESTION # 44
What activities are concurrent to Activity 2001 in the "normal" schedule?
- A. 1001.
- B. 7001.
- C. 1000.
- D. 2003.
Answer: B
NEW QUESTION # 45
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?
- A. Interest rate of owner's construction bonds.
- B. Project variables.
- C. Consideration of all stakeholders.
- D. Value engineering.
Answer: A
NEW QUESTION # 46
Resource planning must take all of the following into account except for
- A. Earned value techniques established for the project.
- B. Cash flow (expenditure) limitations for completing work on the project.
- C. Time available to complete the project.
- D. Types of materials, equipment and labor skills required to complete the project.
Answer: A
NEW QUESTION # 47
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project contract between the contractor and owner
- B. Project justification
- C. Project deliverables
- D. Project objectives in terms of cost, schedule and quality measures
Answer: B
NEW QUESTION # 48
Which of the following is NOT true?
- A. A network must contain only one Critical Path.
- B. Remaining durations can exceed original durations.
- C. Multiple calendars can affect the total float calculation.
- D. Constraints can interfere with the longest path calculation.
Answer: B
NEW QUESTION # 49
......
The PSP certification exam is a rigorous and comprehensive test that covers a wide range of topics related to project planning and scheduling. AACE-PSP exam is designed to evaluate the candidate's ability to apply industry-standard techniques and best practices in the planning and scheduling of projects. AACE-PSP exam covers topics such as project planning, scheduling, progress monitoring, and analysis, as well as cost and risk analysis.
AACE-PSP Deluxe Study Guide with Online Test Engine: https://www.test4sure.com/AACE-PSP-pass4sure-vce.html
NEW 2024 Certification Sample Questions AACE-PSP Dumps & Practice Exam: https://drive.google.com/open?id=11txjznBAEHW0Hj4a_bRiW1kn89RIh72A