[Mar-2022] Verified SAP C_TS422_2020 Bundle Real Exam Dumps PDF [Q40-Q55]

Share

[Mar-2022] Verified SAP C_TS422_2020 Bundle Real Exam Dumps PDF

C_TS422_2020 Dumps PDF New [2022] Ultimate Study Guide


SAP S/4HANA Production Planning and Manufacturing Certification Exam Details:

Passing ScoreC_TS422_2020 - 56%
C_TS422_1909 - 55%
Duration180 mins
Reference BooksTS421, TS422 (SAP S/4HANA 2020)
TS421 (SAP S/4HANA 1909), TS422 (SAP S/4HANA 1909)
LevelAssociate
Schedule ExamSAP Training
Number of Questions80
Exam Price$550 (USD)


SAP C_TS422_2020 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and in‐depth technical skills to participate as a member of a project team in a mentored role.


SAP C_TS422_2020 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Advanced Planning in SAP S/4HANA > 12%

Outline the basics and master data of advanced planning,  explain tools (alert monitor, detailed scheduling planning board) and advanced planning and detailed scheduling processes, explain planning evaluation concepts

Demand Management in SAP S/4HANA < 8%

Explain and compare the different production methods in make-to-order, make-to-stock, and assembly planning.

Lean Manufacturing in SAP S/4HANA 8% - 12%

Identify repetitive manufacturing specific master data, explain line load planning and confirmation, outline Kanban master data and Kanban processes.

Capacity Planning in SAP S/4HANA 8% - 12%

Outline best practices for using SAP S/4HANA, describe the SAP HANA database concept and new user experience with SAP Fiori, outline the capabilities of embedded analytics.

Introduction to SAP S/4HANA Production Planning < 8%

Outline production planning components and functions, differentiate consumption-based planning vs. MRP, outline new trends in production planning.

Production Orders in SAP S/4HANA > 12%

Determine BOM item category, describe order status management and set user statuses, configure availability check for components, trigger routing selection, set up an order type, apply material staging and confirmation.

Introduction to SAP S/4HANA Supply Chain Planning < 8%

Outline both motivation and background of SAP S/4HANA, describe its main components, the lines of business, and the SAP User Experience strategy.

Process Orders in SAP S/4HANA < 8%

Characterize process order elements and process order processing, determine master data objects for process orders, identify features for Good Manufacturing Practices (GMP).


 

NEW QUESTION 40
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. By plant
  • B. By material type
  • C. By industry
  • D. By period

Answer: A,D

 

NEW QUESTION 41
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

  • A. Demand Planning (DP)
  • B. Supply Network Planning (SNP)
  • C. Capacity Requirements Planning (CRP)
  • D. Material Requirements Planning (MRP)

Answer: D

 

NEW QUESTION 42
You are transferring data from SAP S/4HANAIo embedded PP/OS. What master data objects are mapped to a location? There are 3 correct answers to this question.

  • A. Workcenter
  • B. Customer
  • C. Plant
  • D. Supplier

Answer: B,C,D

 

NEW QUESTION 43
In Make-to-order production, which field controls whether the components will be planned as sales order specific stock?

  • A. The Individual/Collective indicator of the component
  • B. The Planning Strategy of the finished product
  • C. The item category of the component in the BOM
  • D. The MRP Type of the component

Answer: A

 

NEW QUESTION 44
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. Scrap percentage
  • B. Quantity
  • C. Item type
  • D. Installation point

Answer: B,D

 

NEW QUESTION 45
Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? Note: There are2 correct answers to this question.

  • A. The maximum mater all number length is 40 for external numbers and 18 for internal numbers.
  • B. The number of leading zeros for internal numbers is client-specific.
  • C. The display template for material numbers applies to all clients.
  • D. In Customizing you can decide by material type whether to use the long material number.

Answer: A,C

 

NEW QUESTION 46
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?

  • A. The requirements date occurs before that of a firmed planned receipt
  • B. The requirements date occurs that of a firmed planned receipt
  • C. The requirement no longer exists
  • D. A firmed planned receipt cannot be rescheduled

Answer: A

 

NEW QUESTION 47
What are pillars of SAP Activate?
There are 2 correct answers to this question.

  • A. Guided Configuration
  • B. SAP Best Practices
  • C. SAP MaxAttention
  • D. Premium engagement

Answer: A,B

 

NEW QUESTION 48
Which task list types can have parallel sequences? There are 2 correct answers to this question.

  • A. Rate routings (R)
  • B. Reference operation sets (S)
  • C. Master recipes (2)
  • D. Routings (N)

Answer: A,D

 

NEW QUESTION 49
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.

  • A. Capacity Requirements Planning (CRP)
  • B. Integrated Business Planning (IBP)
  • C. Material Requirements Planning (MRP)
  • D. Supply Chain Management (SCM)

Answer: B,D

 

NEW QUESTION 50
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

  • A. Reduce the planning window.
  • B. Form optimum sequences to reduce setup times.
  • C. Select an alternative mode on a resource.
  • D. Execute a new production planning run.
  • E. Adjust the available capacity.

Answer: B,C,E

 

NEW QUESTION 51
Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

  • A. Use the material staging report.
  • B. Use the batch information cockpit.
  • C. Use batch determination.
  • D. Use the material where-used report.

Answer: B

 

NEW QUESTION 52
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?

  • A. Top of Red
  • B. Top of Yellow
  • C. Top of Red Base
  • D. Top of Green

Answer: D

 

NEW QUESTION 53
In your project,you have several materials that are planned by different people. How can you assign the planning responsibility?

  • A. MRP controller
  • B. MRP planning file
  • C. MRP type
  • D. MRP group

Answer: A

 

NEW QUESTION 54
A customer is considering switching from order-related settlement to productrelated settlement. What are capabilities of cost collectors? There are 2 correct answers to this question.

  • A. They can be created automatically during month end process.
  • B. They can be used for repetitive manufacturing.
  • C. They can be applied to make-to-stock production order.
  • D. They can be used for manufacturing with collective orders.

Answer: B,C

 