NEW QUESTION # 19
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
- A. Durations of all sprints for the full release defined based on planned complexity.
- B. User Stories are in Ready state for only the first 2 to 3 sprints.
- C. Scope and duration of testing is finalized.
- D. Project scope and planning are completed and final.
Answer: B
NEW QUESTION # 20
Which tools can SAP Cloud ALM leverage for project tasks? Note: There are 2 correct answers to this question.
- A. SAP Readiness Check
- B. SAP Solution Manager
- C. SAP Signavio Process Navigator
- D. SAP Central Business Configuration
Answer: A,D
NEW QUESTION # 21
What accelerator can help you document the configuration definition in the Explore phase?
- A. Backlog template
- B. Business Blueprint document
- C. Data definition
- D. Business Driven Configuration Questionnaire
Answer: A
NEW QUESTION # 22
Which of the following are benefits of using ready-to-use content? Note: There are 2 correct answers to this question.
- A. Predictable results
- B. Fast time-to-value
- C. Maximized total cost of ownership
- D. Exhaustive solution documentation
Answer: A,B
NEW QUESTION # 23
When do you perform Quality Gate (Q-Gate) during a project? Note: There are 2 correct answers to this question.
- A. At the end of Prepare phase
- B. At the end of Realize phase
- C. At the end of Discover phase
- D. At the end of Run phase
Answer: A,B
NEW QUESTION # 24
Which techniques should the SAP Activate practitioner follow? Note: There are 3 correct answers to this question.
- A. Reduce business user involvement for efficiency
- B. Apply the fit-to-standard first mindset
- C. Leverage dynamic extensibility and integrations
- D. Optimize testing by running it only at the end of Realize phase
- E. Use agile approach throughout the project
Answer: B,C,E
NEW QUESTION # 25
What are the capabilities of Task Management application in SAP Cloud ALM with SAP Activate methodology tasks? Note: There are 3 correct answers to this question.
- A. Launch SAP Cloud ALM apps to perform SAP Activate task
- B. Create sub-tasks to break down the SAP Activate task
- C. Delete SAP delivered SAP Activate tasks
- D. Assign SAP Activate task to a team member
- E. Change description of SAP Activate task
Answer: A,B,D
NEW QUESTION # 26
What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct answers to this question.
- A. Establish fixed duration of each sprint.
- B. Sprint duration between 1 week to 4 weeks.
- C. Adjust sprint duration based on team availability.
- D. Set variable sprint duration based on work.
Answer: C,D
NEW QUESTION # 27
What is the objective of a Sprint Retrospective meeting?
- A. Prepare for Quality Gate.
- B. Provide feedback to the project sponsor.
- C. Prioritize the remaining backlog items.
- D. Improve the team's process.
Answer: D
NEW QUESTION # 28
Which artifacts in the Testing workstream are created within the Realize phase? Note: There are 2 correct answers to this question.
- A. Functional Specifications
- B. Test Strategy
- C. User Acceptance Test - Plan
- D. Functional Test Scenarios
Answer: C,D
NEW QUESTION # 29
What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 2 correct answers to this question.
- A. Project management expertise
- B. Process benchmarking expertise
- C. Technology and architecture expertise
- D. Business process expertise
Answer: A,C
NEW QUESTION # 30
Which of the following belong to the Application Design and Configuration workstream in the Explore phase? Note: There are 2 correct answers to this question.
- A. Integration prerequisites confirmation
- B. Fit-to-standard workshop
- C. Change Impact Analysis
- D. Configuration definition
Answer: B,D
NEW QUESTION # 31
What activity do you perform in the Deploy phase?
- A. Implement operations processes
- B. Perform productive cutover
- C. Complete integration testing
- D. Final assessment of data quality
Answer: B
NEW QUESTION # 32
What is an activity that is performed at the end of the Realize phase?
- A. Run the user acceptance test
- B. Load data into production system
- C. Perform cutover simulation
- D. Provision development system
Answer: B
NEW QUESTION # 33
Which applications include content for integration scenarios? Note: There are 2 correct answers to this question.
- A. SAP Business Accelerator Hub
- B. SAP Solution Manager
- C. SAP Cloud Appliance Library
- D. SAP Signavio Process Navigator
Answer: A,D
NEW QUESTION # 34
Where do you activate SAP Best Practices from Cloud ALM to be used during the fit-to-standard workshops for SAP S/4HANA Cloud Public Edition?
- A. Quality System
- B. Production System
- C. Starter System
- D. Development System
Answer: C
NEW QUESTION # 35
......