NEW QUESTION 138
During the 'initiating a project' process, who specifies the required level of management control?

  • A. Project manager
  • B. Project assurance
  • C. Corporate, programme management or customer
  • D. Project board

Answer: D

 

NEW QUESTION 139
Which product identifies how often stakeholders require information?

  • A. Lessons report
  • B. Configuration item record
  • C. Communication management approach
  • D. Benefits management approach

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 140
According to the 'defined roles and responsibilities' principle, what must be represented in the project management team?

  • A. Business, user and supplier interests
  • B. Directing, managing and delivering levels
  • C. Project board, project manager and project assurance roles
  • D. Corporate, programme management or the customer parties

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Define_roles_and_responsibilities

 

NEW QUESTION 141
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2.Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

  • A. Neither 1 or 2 are true
  • B. Only 1 is true
  • C. Only 2 is true
  • D. Both 1 and 2 are true

Answer: A

 

NEW QUESTION 142
Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Obtain approvals for products delivered in a Work Package
  • C. Select and implement actions that will resolve deviations from a plan within tolerance
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: C

 

NEW QUESTION 143
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project Initiation Documentation
  • B. Project mandate
  • C. Benefits Review Plan
  • D. Project Brief

Answer: A

 

NEW QUESTION 144
Why is the 'initiating a project' process used?

  • A. To produce the required work packages
  • B. To decide which project approach is suitable for the project
  • C. To enable corporate or programme management to give authorization to deliver a project
  • D. To fully understand how the project objectives will be achieved before committing significant resources

Answer: D

Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-process-initiating-a-project.php

 

NEW QUESTION 145
Which is a purpose of the plans theme?

  • A. To establish the project's structure of accountability
  • B. To understand whether the targets are achievable
  • C. To identify, assess and control any potential changes to the baseline
  • D. To assess and control uncertainty

Answer: B

Explanation:
Explanation
Reference http://prince2.wiki/Plans

 

NEW QUESTION 146
Which process is used by a Team Manager to coordinate work on one or more of the project's products?

  • A. Initiating a Project
  • B. Managing a Stage Boundary
  • C. Controlling a Stage
  • D. Managing Product Delivery

Answer: D

 

NEW QUESTION 147
Which statement about applying the 'tailor to suit the project' principle is CORRECT?

  • A. A project which is part of a programme should NOT tailor PRINCE2
  • B. The tailoring of PRINCE2 is MOST appropriate for agile projects
  • C. PRINCE2 can be tailored to be used with any type of project
  • D. A technically complex project should NOT tailor PRINCE2

Answer: C

 

NEW QUESTION 148
Which is a purpose of the Controlling a Stage process?

  • A. Produce a Team Plan for the work to be assigned to a Team Manager
  • B. Obtain approvals for products delivered in a Work Package
  • C. Select and implement actions that will resolve deviations from a plan within tolerance
  • D. Update a Project Plan to incorporate the actuals from a Stage Plan

Answer: C

 

NEW QUESTION 149
Which role is responsible for the management of a risk assigned to it?

  • A. Risk owner
  • B. Project Support
  • C. Project Assurance
  • D. Risk actionee

Answer: A

 

NEW QUESTION 150
How does the 'managing product delivery' process ensure that the team manager's perspective is provided in a work package?

  • A. The team plans are checked by project assurance against the work packages
  • B. the work packages provided by the project manager are agreed by the team manager
  • C. The stage plan covering the work packages is created with input from the team manager
  • D. The work packages are defined by the team manager and supported by a team plan

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 151
How does the project board use the 'manage by stages' principle to control the project?

  • A. By approving the project management team
  • B. By ensuring that the benefits are managed and controlled
  • C. By reviewing project viability at defined intervals
  • D. By reviewing previous project closure documentation

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_stages

 

NEW QUESTION 152
Which is a purpose of the Directing a Project process?

  • A. Ensure that work on products allocated to the team is authorized and agreed
  • B. Create and authorize the project mandate
  • C. Delegate day-to-day management of the project to the Project Manager
  • D. Control the day-to-day running of the project

Answer: C

 

NEW QUESTION 153
Which is a benefit of using PRINCE2?

  • A. Can be applied to any type of project
  • B. Can be tailored by leaving out elements of the method for some projects
  • C. Avoids the need to involve corporate or programme management
  • D. Enables the management of projects as well as of 'business as usual' activities

Answer: A

 

NEW QUESTION 154
Which describes risk probability?

  • A. Timeframe within which the risk may occur
  • B. Level of risks which the project can tolerate before escalating to the Project Board
  • C. Probable effect on the project delivering its objectives
  • D. A measure of the likelihood of the risk occurring

Answer: D

 

NEW QUESTION 155
Which is a true statement about PRINCE2 event-driven controls?

  • A. Event-driven controls take place at predefined periodic intervals
  • B. Checkpoint Reports are event-driven controls
  • C. Event-driven controls are produced at the frequency defined in a Work Package
  • D. Event-driven controls are used for decision making

Answer: D

 

NEW QUESTION 156
What theme provides the justification for the project?

  • A. Business Case
  • B. Quality
  • C. Plans
  • D. Progress

Answer: A

 

NEW QUESTION 157
Which is an objective of the Directing a Project process?

  • A. Create and authorize the project mandate
  • B. Control the day-to-day running of the project
  • C. Provide accurate progress information to the Project Manager
  • D. Provide management control and direction

Answer: D

 

NEW QUESTION 158
What is a benefits management approach used to assess?

  • A. How the project has progressed against its plans
  • B. How the project's products have performed when in operational use
  • C. The suitability of the project management team structure
  • D. The effectiveness of the project strategies

Answer: B

Explanation:
Explanation/Reference:
Reference https://mplaza.pm/prince2-benefits-management-approach-template/

 

NEW QUESTION 159
Which is an objective of the Starting up a Project process?

  • A. Agree how issues and changes will be identified, assessed and controlled
  • B. Agree how the project will be monitored and controlled after initiation
  • C. Identify who will be responsible for creating the Project Plan
  • D. Authorize the Project Manager to proceed with the initiation stage

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 160
Which is a purpose of a Project Product Description?

  • A. Defines what the project must deliver in order to gain acceptance
  • B. Records the costs and timescales for delivery of the project's final product
  • C. Shows the dependencies between the project's products to aid planning
  • D. Provides a list of all the products to be delivered by the project

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 161
......

Actual PR2F Exam Recently Updated Questions with Free Demo: https://www.test4sure.com/PR2F-pass4sure-vce.html

Free EXIN PR2F Exam Questions: https://drive.google.com/open?id=1HRDF1JJMioi_wOyMhwcR-ZfGA2wUdzMH